Monday, December 6, 2010

First Year of Construction: Nov. & Dec. 2007



When I first began writing this blog I had already been working on the house for about a year and a half. My wife set it up for me and insisted I keep a journal of what I was doing. My account pretty much begins at that point, when the walls and roof were already built and there was electricity flowing into the house. By the time I began writing, the house was relatively comfortable. So there is a big gap up to that point in my story to anyone who wishes to follow my adventure from the beginning. I have added some prequels in between, the last one ending with my trip in October of 2007 (please refer to the entry of Feb.4 2010: First Year of Construction: Oct. 2007) when my parents came to visit and we started building a platform for a somewhat temporary shack which was meant to be an addition to the current tiny living quarters of a slide-on truck camper built in the 1970s. The "addition" was meant to solve some heating and storage issues I had with the little camper, but in retrospect I can't help but wonder "what was I thinking?" Why didn't I simply build a small box off the camper and be done with it? I would still have had a place to store my tools and a shelter for a wood burning stove to solve my heating woes. It could have been done after only a couple of visits. It didn't need to be any more complicated than my outhouse. Instead I have erected a monstrosity from almost no plans that has now eaten the camper and continues to grow and envelope a nearby tree. Most disturbing of all is that this mass of wood, metal and glass has a foundation originally meant for a shack. I've since beefed it up with stone and more "feet" but it is not set deep enough for any kind of permanent structure. It just sort of "floats" on the ground. It's like a ship at sea now resigned to dip and heave in the ocean of soil and rock to be torn apart by the whims of the Earth. There are no signs of damage by frost heave yet but I fear that soon the rocking of the ground will show it's strength. First the doors and windows will get sticky. Little by little the frame will turn from a cube to a trapezoid; only slightly at first but as the years pass the frame's shifting will loosen the sheathing and everything else with it. The corners will open up with triangular holes and the roof will buckle and open up the interior to rain. Water will drip drip drip into all the corners and passageways as water likes to do, bringing with it rot. The house's bones will become brittle and break under it's own weight. The house will implode and eventually be scattered by the wind leaving only two old oil drums that once held up a slide-on truck camper built in the 1970s.
Perhaps it is a fitting end. And perhaps I should save sharing my fear of death for another entry.

For now I just want to close the gap in the history of this project. I did return in November of 2007. At that time I was spending only about 3 days a (winter) month on the project so progress was slow. This was due to a few factors some having to do with my work situation on Cape Cod and partly due to power limitations. I had no electricity yet. I did all my cutting for construction with a Stihl chainsaw. The only other usable tools I had was a cordless drill and jigsaw. Each had a battery that was also interchangeable with a utility light which got a lot of use in the evening. The camper's power source was a couple of old car batteries that I soon replaced with one deep cycle RV battery. The camper's battery could easily power it's small interior lights for days on end but the propane heater was coupled to a fan on a thermostat. Kicking on the heater also meant running the fan. The camper was so flimsy and marginally insulated that even with the thermostat set at 50 degrees (it's lowest setting) the heater was kicking on every few minutes and ran continuously when it was really cold outside. It was so inefficient that after only a few nights the battery was dead and my propane tank dry. I spent some very cold nights in a soggy camper with a heater that barely worked. I could have bought some more batteries and more propane tanks but as has been the case throughout this project I did have (and do have) a very limited budget. To add to the discomfort of the leaky camper it was also home to an extended family of mice who stayed up all night scratching and clawing at the inner walls. I caught dozens in traps but there were always more to take their place. I had reoccurring dreams in which armies of little grey mice clawed and nibbled on my feet and face while I slept. I really wanted a new place to sleep. I figured that as soon as the first floor's sheathing and windows were in place I could erect a make shift roof and heat myself with the wood stove and sleep next it on an old couch or something.

By the end of that November visit I had nailed up all of the OSB sheathing, installed four windows (I had bought used for $20 each locally) framed and covered the second floor with 1" hemlock. There were still some large openings left open to the world: two post and beam framed "doorways" in the eastern and western sides, and the landing between the camper and the "house" which was closed on all sides but open to the sky. There ended my November visit. I threw a tarp over the open landing and put a few sheets of plywood and metal roofing on the second floor to have a sort of roof to keep the interior dry. It didn't work...

DECEMBER 2007

More than a foot of snow had fallen since my last visit. I shifted my pickup into four wheel drive and plowed through the snow, wheels spinning until I reached the top of the little plateau where my shack stood. I had with me a load of furniture donated by the Bennett/Tasha family of Truro. The load included a recliner a dresser and a couch that I intended to sleep on that night. It was already late afternoon, sky darkening and the house was full of snow. The tarp I had hung at the close of my previous visit had filled up with snow and now hung like a sack between the back of the camper and the second floor of the house. Casting it loose was not an easy task and as soon as I did the snow ended up piled on the floor of the landing. I would have been better off not hanging the tarp at all. By then it was almost completely dark. I donned my head-light flashlight and lit my propane lantern. I started a fire in the stove and got it going good and hot. I then shoveled out the majority of the snow around the stove.
Now I needed to enclose the stove so I could sleep next to it. The stove already had the make-shift roof of the second floor and on top of that I had laid sheets of metal roofing and plywood to cover the slats. The walls, however still had three gaping holes. I covered the door opening in the eastern wall by nailing a sheet of plywood over it. Then with a couple of tarps I made a wall over the opening to the landing which was still open to the sky and full of snow. It was also my route to the camper and it's kitchen. I hung the tarps in such a way that I could slip in and out. With the last opening in the western wall I was going high tech with an actual door. I had found a pre-hung exterior door in a dumpster months earlier and I had saved it for this very occasion. Being already hung in a frame and with a header already in place in the wall it went up relatively quickly. I closed up the last small gaps around the frame with a few pieces of plywood. Boom! Done! Milestone: a new place to sleep. The enclosure was already beginning to hold heat. I dragged the couch out of the truck and into the shack and set it in the snow next to the stove. It was late in the evening by then and I was going to sleep well tonight! Or so I thought. Sleeping on a couch next to the stove was cold and cramped. I bundled up well but dreaded each time during the night when I had to get up to reload the stove or go pee in my pee-jar. Still, it was better than the camper which in turn was better than a tent. I was moving up in the world.

I awoke the next morning with gusto. It was time to frame out the second floor which meant a roof was soon to come. I started out building on a sunny morning with what 2X6s I had left over from before. I soon ran out but was low on money and could not afford to buy more. I did, however have some pressure treated 2X6's that I had salvaged from a demolition on the Cape. So I used those. In retrospect I should not have done that. It was a waste of good pressure treated wood and it was very difficult to nail together. Every other nail I tried to drive in would bend. Eventually I built graduated walls that could carry the weight of the pitched saltbox roof at several points. I also added a dormer facing south that was not in my original plans but when a clear evening sunset brought to my attention how nice it would be to have a point from which to gaze upon future sunsets I decided to build one. So with pressure treated studs in the upper floor it would last forever. At the same time I noticed that some of the studs in the lower walls were already showing signs of rot. I guess I should have taken a better look at them before pulling them from the discard pile at the lumber yard. As I have done many times before and as I have done many times since, I reproached myself for being so careless. So stupid to have let that go unnoticed. I am blessed with a respectable amount of will-power but am capable of astonishing lapses in judgement. That can be a dangerous combination.. I must remind myself always to be careful and think things through.

So with the second level walls framed, my few days visit to Maine was at an end and I needed to get back to the Cape. Before leaving I stood on the second floor and imagined what it would feel like when the walls were closed up and the roof in place. A far sight warmer, that's for sure! But also I imagined a feeling of protection and sanctuary.
Somewhere in the middle of the framing process during which I was trying to nail together boards that seemed to be made of stone, I had one of those moments that was simply remarkable. The sun setting low in the sky cast a celestial light of Devil's Red across the snow and the trees. The quiet in those woods was so pure and extraordinary that I had to pause and take in all that was around me. My soul felt full of joy and gratitude and I knew that I had found the path I was looking for. In spite of whatever mistakes or lack of patience or stupidity that I had and would display in the process of this undertaking I would be taken care of; I was a part of some sort of Great Spirit or Oneness; and this project and this land was my Way towards it. Nowhere have I ever been able to experience such states of being with any kind of consistency but on this land. No doubt this is a religious experience.
Now it was time to return to the world of the Living with work and rules. I packed the truck, said farewell to the shack and headed south.

Thursday, December 2, 2010

Nov.2010 A Vehicle of Salvation



It was a great milestone to have an indoor toilet but I was far from living comfortably. The new entryway to the kitchen was very much unfinished, leaving a gaping hole in the side of the camper which I had only temporarily closed up with a sheet of plywood. There were still many gaps in the side of the house where not only cold air could enter but warm air could escape. Keeping warmth inside the kitchen has been challenging from the beginning. The warm air from the stove tends to go upstairs and only begrudgingly finds it's way into the off shoot of the kitchen. I need it to be closed up for the coming winter cold.
The kitchen has for the last year been a bare bones structure and a major source of air leaks. There is a lot here to do because not only am I creating a new entryway but also another level above it that will be coupled to most of the kitchen. In the distant future it will serve as an indoor greenhouse and part of some sort of tower.. for the near future it will serve the purpose of much needed storage with a temporary roof.
So after christening the septic I turned my attention to constructing the rest of the floor for the second level next to the kitchen. Part of it I had already built but I wanted it to extend all the way to the adjacent (exterior) wall of the upstairs bedroom.
So with two full days remaining in this visit, I started by framing out a couple of walls that would enclose the lower level and one that connected the entryway with the (exterior) living room wall. In the future this will serve as a wall for the garage. For now it would support the stingers for the above floor which will also be a small deck, all of which will eventually create a sort of enclosure around the first ten feet of the trunk of the Pine. After installing the stringers I was able to complete the floor/deck of the second level. I reached this point late in the evening of the last remaining day, a Saturday. I had cut and fitted all the boards for the floor but was too cold and exhausted to continue. I would finish it the next morning before I left.

Last day, time to go. It always comes down to this. I remember this feeling from when I was a kid. It is one of profound disappointment. Summer vacation is over. Must go to back to school. Go back to the world of people who will look at me and judge me and expect me to be and do as I am told; tasks I do not care to do, events that hold little meaning for me, rules to follow and a schedule to keep. I do not care for "life as we know it". My usual routine and my job, as ideal as I've managed to make it, seems drab and ridiculous to me now that the house exists. The house is what matters to me most now. It is the vehicle of my salvation, my Jesus Christ. It's progress is fused with the cells of my blood. It is the refuge I sought as a kid but found only elusive in imagination; left searching always searching as a young adult for something real, eventually drowning myself in alcohol and self pity out of sheer frustration. I was looking for an intangible ideal in a world of illusion; a knowing of some sort that religious people seemed to possess. Over the years I came to believe the thing I was looking for was within and I turned my attention there. I studied religion, astrology and meditation. I tried lots of psychotropic drugs and scrambled my brains and then tried living sober and the world became flat and predictable. Eastern religion held much promise. I knew there was truth there, a common thread in all religions. But how to access it? Sitting in churches and meeting places and study groups did not offer a meaningful answer. The truth was always in front of me and I knew that, but I did not feel it; or rather I was not a part of it. I could never really feel like I was a part of anything. Any social activity would only accent my separateness and continues to this day. Meditation seemed most promising but again I could not resign myself to it. To do it completely was to dismiss all things material and did not explain to me the purpose behind all this that I see and imagine around me. Perhaps I was young and impatient but divorcing myself from the material world did not seem like a path I could follow. Then came the land and the genesis of this weird little house. I felt an awakening and a compelling feeling of "must do". Upon purchasing this land a path had been opened up to me. The more I build the richer I feel. It is a conduit of unadulterated joy and profound anxiety. The further it progresses the deeper I go... this house is me.

Wednesday, November 17, 2010

Nov. 2010: Septic System, part 3


We arrived, my cat and I, in the afternoon of Sun Nov.7. After feeding Boo Boo I began the usual chores of opening the house. I turned on the electricity and made a fire in the stove. I unloaded the truck, unlocked and started the tractor and got the water pump going. By the time I had settled in, daylight was all gone so I busied myself with cleaning up the bathroom area which by this time had become a sort of storage closet. My goal during this visit was to have indoor plumbing by the time I left in a week. At this point my septic system consisted of a drainage field and a septic tank. The 4" drainage lines where partially assembled under the house by me and my dad during the previous visit but they had not been finished to the point of entering the house through the floor or glued together.
I got up early the next morning. It was raining and gray but not cold for November. My first task was to finish assembling the main drain pipes: a dirty job I did not relish doing. There were two sections to complete. One line was under the living room floor and needed to enter the house behind the stove to connect with the bathroom upstairs. The other branched off the main line and extended to the far end of the kitchen. This line also needed to come up through the floor so that all the remaining plumbing would be interior work.
I started with the line under the living room. I donned my orange jump suit as coveralls and crawled under the house with as many tools as I could drag along with me. It took many trips back and forth to get all of my materials under there. I connected a "T" joint to the end of the 4" line with a 3" inlet and a clean out plug. After cutting a hole in the floor with my sawzall I was able to run the 3" line into the house with a 90 degree turn. It had to be a tight turn to meet the gentle slope of the rest of the line. From there I began to join it all together with a special glue for PVC pipe. Little by little I dragged myself along through the dirt and cemented each joint and hung the pipe with metal straps screwed into the floor stringers. It was such a dark, cramped and dirty job I hated to even think what to do if any of it leaked. When I got to the line under the kitchen I spliced in a similar section as the first off the main line to bring a 3" pipe up through the floor. It was late Monday night after a 13 hour day when I finished. Early the next morning I pressure tested the main drain lines. I did this by capping the end at the septic tank and filling the pipes with water (the volume is great enough to create about 5 lbs. of pressure). I then crawled under the house with a utility light. I groaned and cursed as water sprayed from most of the joints I had fitted the day before.
I laid in the dirt for a moment to collect my thoughts. It was not the end of the world. It didn't leak everywhere. At least the 3" sections going into the house were both water tight. The leaking parts were all concentrated where the main kitchen and bathroom lines connected. There were a lot of fittings in the area.. why was it leaking? I must not have used enough glue.
With three swift cuts of my Sawzall I removed the entire leaking section in a giant Y. After another trip to Buxton's building supply and a few hours time the line was complete again. Before a second test I wanted to give the glue a few hours to dry. In the meantime I began to assemble the drains and vents from the bathroom. This included a trap and vent for the shower, same for the bathroom sink and the waste line for the toilet. Most of this was concentrated in the wall behind the stove. The venting of the lines took the most thought, although it's actually not so complicated. It just took a bit of "sinking in" after reading up on the concept to understand how the air in a pipe is displaced by the water running through it. Anywhere in the line that water is going to run there must be an escape route for the air that otherwise occupies the volume of the pipe. For the function of smooth drainage the air must be able to vent out an open stack, in this case a pipe that exit's through the roof.
That Wednesday evening I tested the main drain again. Again it failed to hold water. It wasn't nearly the colander it was before but it had enough drips that I would have to redo the same section for a third time. Fuck.
On Thursday afternoon, main drain fixed again and an exhaust pipe out the roof , Randy the plumbing inspector dropped by and approved my work. This was monumental. I was within spitting distance of the apex of this project: flushing a deuce.
For the third time I filled the main drain lines with water and this time it held. I then joined the main drain to the septic tank to complete the entire system. Done! I decided to take this monstrosity on it's maiden voyage the next morning when I am usually ready to do my business. I wanted to give all my fittings time to cure.
I arose early Friday morning. I looked everything over and decided it was time for the moment of truth. I turned on the water at the pump...good! No leaks in the waterline. I turned on the valves at the bathroom sink and toilet tank and turned the water to full blast. I flushed the toilet several times and went downstairs to watch the pipes and then crawled under the house for one last inspection. All seemed good except for a leak at the trap under the sink which I quickly mended. It was 7:30am and my own bodily plumbing was ready for a flush so I settled myself upon the throne.
I am pleased to report it was a most satisfying expulsion.

Saturday, October 30, 2010

Oct. 2010: Septic system, part 2



My folks had rented a hotel room for the next several days. I rode into Belfast with them (about a 20 minute drive) to have dinner and take a shower. A hot shower is such a luxury when you do not have one at your convenience! When staying at the house sculpture I take sponge baths with water heated on the stove. After this visit, I am much closer to having a hot shower at home. I still have yet to sculpt a shower stall..
I stayed at the hotel that night with my folks. When we awoke the next morning it was pouring rain. It continued to rain after we had arrived at the house. It put me in a lousy mood and I did not feel like working but Mom and Dad seemed determined to get some shit done. Two projects were high on my list of priorities. One was to assemble all of the 4" waste pipe underneath the house. The other was to level the bed for the septic tank which needed to be finished today as the tank would be delivered the next morning. I had already dug the pit, but it needed sand to be thrown in to make a level 6'X8' bed. Thanks to the rain the pit now had about a foot of standing water, so I suggested we work on the waste line and wait until later in the day when the rain might let up. That was all my Dad needed to hear. He immediately went outside and crawled under the house. It was still pouring outside and there was mud everywhere. As dirty a job it is to be crawling around under the house it was at least dry. So we assessed the situation, figured out what we needed to do and got to work. I knew where the 3" line from the bathroom would need to exit the floor to the underside of the house and meet the 4"pipe so we started there and ran the pipes on around to the center of the house and aimed them toward the septic tank some 40 or so feet away. We added a T in the line so that we could connect a waste line running from the kitchen which we also hung. We pitched the line at 1/4" per foot which is standard code. After a couple of hours all the pipe had been hung and Mom had a delicious lunch ready for us. We were covered with dirt. The combination of getting wet with rain and then crawling around in the dry dust under the house outfitted each of us with a thorough coating of mud.
The rain was letting a bit after lunch so we decided to make the pit ready to receive the tank. My folks were all into doing the dirty work of standing in the pit raking while I dumped in sand with the tractor. The standing water in the hole actually helped determine a level grade. After awhile a nice bed had been made and we were ready for the tank.
I stayed at the house that night and met the truck delivering the tank early the next morning. It was a huge truck with a hydraulic lift off the back. The driver was good. He backed his truck all the way up my driveway and up to the hole. By remote, the driver used the lift to pick the 2 ton cement tank off the truck and set it gently on it's level bed of sand.
With the tank in place it was time to build the drainage field. We set to work leveling each course with sand and setting in three 10ft. sections for each of the five courses to make a total of 150ft.. Each course ran at 4" graduated elevations which we were able to determine with the site leveler. It took us a couple of days to install all the enviroseptic lines. When the pipes were in their places we capped and linked them together with 4"pipe. Last, we joined the drainage field to the septic tank and the tank to the house.
Now it was time to call Randy the inspector to come out and take a look.
Randy would come by the next morning so it the meantime my Dad and I turned our attention to the roof of the house. During the recent rain storm the house had showed some leaks. Eventually we made an educated guess as to where the water was getting in and made the necessary repairs.
The next day Randy came out and measured our work against the nail in the fir tree. All was good! We had passed inspection and were ready to backfill. The entire system needed to be buried 18" deep from the top of the drainage pipe. We had some sand left so we buried the drainage area, but only just barely. There would need to be much more backfill later. For now this visit had come to it's end.
It was time for a sad farewell to my folks who were flying back to Oregon the next morning. I am always amazed at my parent's willingness to travel such a long distance and do so much physical work for the sake of me and this little shack in the woods. For myself, I decided that I was done too. I was tired and missed my wife and needed to be back at work on the Cape. As always, leaving my little haven in the woods was a painful experience. I've invested so much of myself in this thing and in the process have grown very close to my parents. Now at three years into this project, I care so much for what of myself and my family it embodies, I can't help but tear up with sadness every time I must leave.

Tuesday, October 26, 2010

Oct. 2010: Septic system, part 1



The time was nigh for a long put off project. I had been trying to wrap my mind around this certain necessity since before I began building the house sculpture. During this October visit, three years into the project, I, with the help of my parents (yet to arrive) would build a code septic system. I had plans drawn up, but the building process was still foggy in my mind. As usual it was my intention to learn as I went along, one step at a time. I knew I would need a lot of gravel and sand so I called a local contractor, Steve Roche. He had brought me fill for my driveway the previous year and the locals spoke highly of him. Steve also turned out to be helpful whenever I had questions regarding the construction of the system as he had built a few of this type himself. This sort of design is called an enviroseptic system because of the special pipe used in the drainage field. Each length is 10 ft. long and 12 inches in diameter. Each piece is ribbed, perforated plastic wrapped in a filter cloth.
I also knew I would need a site leveler to know at what depth in the soil to place each row of the enviroseptic drainage pipe. Ted Pellerin, who had designed my system, offered to let me borrow one of his. It was an old fashioned sort, just fine for what I was up to.
With the leveling device I could determine how much from grade level to take off of the drainage field. I first made some 8ft. stakes to mark the four corners of the field. They needed to be tall in order to pass level of the fixed point at which the system would be built: a nail in a small fir tree nearby. Ted had picked this point and sited everything against it. By lining up the leveler with the nail, and aligning it to my stakes I could calculate how deep I needed to dig for the pipes to sit in their proper places: seems I still needed to take away another foot of dirt. More tractor time!
With the tractor's backhoe I lowered the grade level by about a foot. By that time Steve had delivered two loads of fill, one gravel and one sand. I used this material to build a berm on the lowest side of the drainage field. The lowest side would need to be built up more than the other three; about 30" from grade level. At this point I turned my attention to the location of the future septic tank. I needed to dig a large pit located between the house and the drainage field. The tank would need to sit at a depth relative to the waste pipe coming from the house. Set at a slight angle of 1/4" per foot, the pipe could enter the inlet flange at 54.5" from the bottom of the tank. The depth would change in accord with it's distance from the house. The plans called for a standard 1000 gallon tank which measures about 6ft. X 8ft. side to side and about 6ft. tall, (54.5" to the bottom of the inlet).
I had already measured and positioned the 4" waste pipe's angle starting where the main interior drain would be located under the house to where it would exit the side of the house. Knowing that height I was able to extrapolate the depth of the tank. I wanted to put the tank as far from the house as possible because it must by code be located at least 10ft. from any structure. My future plans for the house involve an addition to this side of the existing house. The location of the tank would therefore dictate how wide my addition could be. I thus began digging next to the drainage field. A big concern when digging in Maine is stone ledge. It's everywhere and makes digging to any great depth very difficult. In my case I needed to have a pit that was about 5ft. deep. With an excavator that isn't too difficult to achieve but with my little backhoe it's a little trickier. I had to dig around a bit and displace a lot of dirt and large stone before finding the spot where a level 6'X8' bed could be made.
It was at this point on a Thursday afternoon that some very welcome guests arrived. It was my parents all the way from Roseburg, OR to help with the completion of this mighty project.

Thursday, October 7, 2010

September 2010

At the end of September, Sprocket and I arrived at the House Sculpture. It was still early afternoon so I had some daylight to accomplish something. The clearing for the septic still needed finishing before the inspector could come by and look at it, so I started up the tractor and got to work. I called him the next day; I think it was Tuesday. He said he could come by on Thursday evening, so I had a couple of days to turn my attention to the house and it's awkward kitchen. I have noted during several past visits the cramped feeling of the kitchen. Some part needed fixing or "adjustment". The culprit was within the camper section for sure, specifically the spot where the old RV refrigerator was located. I also had decided months before that the entryway was not right. The exterior door must be moved. Really, the whole kitchen needed to be pushed out and that meant more floor which meant more foundation.
Before I began working I did some thinking. I do lot's of standing around thinking. I wanted to picture how the upper floor would relate to the lower. The new section would be squared to the living room section with a second floor deck, I surmised, which will have an entrance from the second floor future master bedroom... and there might be some funky tower in there too. All that will sit upon a garage/ workshop area which will also serve as a seasonal dining room or a place for guests...or something like that...
First I figured out how a wall, square to the box of the house that was the living room, would meet the porch that extended off the kitchen. I then cleared and leveled two spots where two heavy "feet" would need to be located in order to support a load bearing wall that could eventually run flush with the living room. I made the feet with my usual method of placing two 8"X8"X16" cinder blocks together and filling them with concrete. The legs consisted of pressure treated 4"X4" blocks with treated 2"X6"s attached to form "I"s. I bridged them with a thick beam of rough-cut Hemlock. The span had to be rather long, about 8ft.. The floor's close proximity to the Pine tree that will eventually be at the center of the completed house made me want to tread lightly so as not to damage any roots.
When the stringers were in place and anchored to the deck it was time to put the sub floor down. But first I had to cut away another section of the camper (about 44") so that the floor could meet the camper's floor flush and attach securely. I first moved the old RV fridge and propane heater. I began cutting with the Saws-all and Kitty made herself scarce. She always knows when I'm about to make a racket. It's always a messy job removing bits of the camper. Shortly I had yet again cut away a section of my original "house" on this land. Now all that remained was a 6ft. section of what was once the camper's tiny bathroom.
With the removal of that section, the fen Sui immediately improved. Now, in my mind's eye I could see all the kitchen appliances, shelves and cabinets falling easily into their places. It was a stark contrast to my previous mental arrangement of a losing game of Tetris.
At this point in the day, late afternoon Thursday, my time was limited to close up the opening in the wall, but it was also time for the inspector to arrive. And he did just before 6pm.
As before, he had no concerns about my haphazard building style. He took a long look at the clearing I had made and at the plans Ted had drawn up for the septic system. He issued me a permit to continue with my plan, but expressed concerns about my narrow winding driveway. It may have to be widened to get a dump truck up there for the many loads of fill it will take to complete this septic project. But that is for another time, soon to come!

Tuesday, August 24, 2010

August 2010





My busy work schedule during the summer season rarely gives me an opportunity to get to Maine. Luckily, at the end of August we were graced with the visit of three lovely female tattoo artists from Philly. As much as I would enjoy their company as work mates, the time was ripe for me to excuse myself and take a trip to the woods. As a person who treasures his times of solitude, the hoards of tourists on the Cape can make me very uncomfortable over the period of summer months. That many people jammed into one space makes my skin crawl. I feel like I'm immersed in some kind of human ant colony. Provincetown and the outer cape takes on the inertia of the colony: continuous, mindless movement of doing and taking and consuming. More and more ants arrive all the time, filling the limited land mass and septic tanks to capacity, all with the same frantic goal of relaxation. They all do it together, all at the same time. It's what people do and that makes it okay. That's normal. normal scares me.
It is my ultimate goal to live in the house sculpture. It's location in the great North woods with it's "hearty" winters gives my wife pause.. but she's up to give living there a try, under expected conditions: there must be functional, modern plumbing. I would want nothing less for my lovely bride. The point is she's into it! All I have to do install a septic system, sewer pipe, drain pipe, vent pipe, water lines, fixtures and appliances. Easy. I suppose I must finish building the kitchen and bathroom too... All that may take awhile. I absolutely must spent a great amount of time in Maine this winter and finish this house!
Now this is more than just coaxing my girl into living with me in some shack in the wilderness. Having a house to live in on property I own (and will own outright in a few years) means something. It means that I will have created a home for a family that is solid and payed for. It will be a place for dogs and cats and kids to run amuck making adventures and a great many other things, thanks to the possibilities that a good chunk of property affords. The community around it is no economic power dome but it is a very friendly, self sufficient community. It is a good place for a kid to grow up and learn many useful skills. I might not make as much money up there as in other places like Cape Cod or New York but I won't need to. I would only have to make a fraction and could still support a small family. My expenses are already low as this place is concerned. Over the next few years they will only go down as the tractor and land is paid off. That leaves only food, utilities, insurance (blaugh) and of course taxes. Not much. If all goes well I maybe able to set aside a few bucks for the kids to go to college or mortuary school or whatever... but I suppose I am getting ahead of myself...
For the present I need to focus on this septic system. This alone is no small task and will likely be the most costly project connected to this entire undertaking. First thing I did
was call Ted Pellerin, the local soil tester. I needed him to look at my site, test the soil and stake out the location. I had arrived Thursday evening and was going to be there until I had to leave on Monday morning. Ted came by on Friday afternoon. He had been there before when I first bought the property and had tentative plans to build some kind of camp but my plans had since changed. He was surprised to see how much it had grown up over the last few years and was delighted to see what I had been up to. "It's a hippie house!" he exclaimed. He was really into the whole project and was hoping to do something similar to make retirement affordable. The next day he came by to show his wife. I was really happy to get such positive feedback from one of the locals.
After the site had been determined and test pits dug to determine drainage capacity, I was ready to start clearing the area. I sharpened the chains on my chainsaws and mixed a new batch of fuel. I felled several trees and cut them into firewood. I loaded the pieces into my truck and took to the porch on the other side of the house and stacked them into rows. After repeating this process a couple of times I was ready to do some work with the backhoe. After the tractor was warmed up and lubed I proceeded to rip out the stumps of the trees I had cut as well as those cut by Skip, the logger before I owned the land. Pulling stumps with a backhoe can go quickly if the stump is small or many years old but can be big projects as with big hardwoods like maple and oak. In any case removal involves digging around the stump and severing the roots until the hoe can pull it free. At that point I wrap the backhoe's arm around the stump like a bully putting a kid in a head lock and drag it to my big brush pile at the edge of the property where I drop it with all the other stumps.
Over the course of my three day stay I managed to clear the area of trees and stumps and cut and stack a fair amount of firewood for the upcoming winter. I had hoped to get some work done on the house, but alas it was not to be. I gathered up Sprocket my cat and headed back to the Cape.